Restoration Works at the Grand Master Palace

10 November 2026

The restoration of the Grandmaster’s Palace has been underway for years, with de Valier carrying out extensive works across the building. As the project continues, we take a closer look at one phase above the Dining Room, where replacing the roof meant protecting the timber coffered ceiling directly beneath it.

The brief was to remove the existing concrete structure and recreate the original pitched timber roof, which was destroyed during the Second World War. That meant working out how to dismantle and rebuild the roof while keeping the historic ceiling and the rooms below protected throughout.

The restoration of the Grandmaster’s Palace involves careful structural works to preserve the building’s historical character while ensuring its long-term protection. One of the key phases involves replacing the existing concrete roof structure with a replica of the original timber pitched roof, which was destroyed during World War II.

Preparatory Works and Structural Removal

This phase of works involved the replacement of an existing concrete roof structure, comprising a concrete slab and steel beams embedded within masonry walls, situated above a self-supporting timber coffered ceiling. Given the heritage significance and vulnerability of the underlying structure, the dismantling process was carried out with particular care.

Before work commenced, a temporary steel-and-timber canopy was erected to protect the exposed areas from adverse weather conditions. Associated restoration works were also undertaken to ensure the waterproofing of all exposed surfaces and prevent water ingress into the palace halls.

Following completion of the preparatory works, the concrete slab was cut into pre-determined sections to facilitate its safe removal down to St George’s Square. The steel beams were subsequently removed.

Reconstructing the Original Timber Roof

One of the biggest challenges during the removal of the existing concrete roof was managing the water generated when cutting the concrete slab, as the concrete saw required a continuous water supply. To address this, a custom-made water collection system was designed and engineered alongside the temporary protective canopy. This system was designed to prevent water from leaking onto the existing soffit beneath the slab, protecting the historic finishes and underlying structure. The process required careful planning and coordination to ensure the works could be carried out safely without damaging the building’s historic fabric.

Once the concrete slab and steel beams had been carefully dismantled, the elements of the new timber roof structure were delivered to site.

The seven primary frames were pre-assembled in St George’s Square and carefully lifted into position. Once aligned, the frames were clad with prefabricated sandwich timber panels to form the new pitched roof enclosure.

This reconstruction aims to replicate the original wooden pitched roof, restoring an important architectural feature of the historic palace.

Waterproofing and Ongoing Works

Following the installation of the new timber roof structure, a waterproofing system was applied to the external roof surfaces to protect the building against water ingress.

The remaining works, which are ongoing, include the installation of the support system connecting the coffered ceiling to the new roof structure, modifications to the gable-end masonry wall, the construction of gutters at both ends of the roof, and the installation of a new HVAC system to service the Dining Room below.

These works form an important part of the ongoing restoration of the Grandmaster’s Palace, combining structural improvements with careful attention to the building’s architectural and historical significance.